Separation & concentration heavy minerals from the valley deposits |
Project Name |
|
South Sinai (industrial zone) |
Project Location |
|
Wade khroum ,Wade El Att – Southern Sinai = 92million tons |
Project Reserve |
|
1.classification & exploitation of valley deposits in eastern Wade El Att and its tributaries
2.Production of feldspar of different sizes , Quartz , zircon , Alalimit , Almagnite and silicate minerals
|
Project Objective |
|
1.Achieve high added value due to the adoption of the project on local natural resources available
2. providing 70 job opportunities
3.Increasing the volume of experts
|
Project Description |
|
Extraction of feldspar ore, Quartz and some of dark minerals in large quantities (3 million tons per year ) |
Production Capacity |
|
One year |
Duration of Implementation |
|
25 years |
Project Time scale |
|
Almost 20 million pounds |
Total Cost |
|
Almost 25 million pounds |
Net Profit |
|
The Egyptian Mineral Resources Authority (EMRA) |
Responsible Entity for the Project |
|
(EMRA) 50% , partner 50% |
Earning ratio |
|
The project will be financed by the joint venture company , which will recover its expenses after the production. By the end of the project the ownership will be transferred to EMRA. |
financing |
|
2010 |
Start up date |
|
Project proposed for investment |
Current Status |